California plan-reading practiceFraming and structural components

Loading questions…

Study this topic as flashcards

Rules to remember3 key framing and structural components rulesShow the rules
  1. The index pairs W2 openings with detail 7 on sheet S5. (p. 2, Contractor Test HQ · original project drawing schedules (opens the official source))
  2. An uninterrupted W1 run uses detail 3 on sheet S5. (p. 2, Contractor Test HQ · original project drawing schedules (opens the official source))
  3. At door 22 the frame type alone selects J3 under the schedule. (p. 7, Contractor Test HQ · original project drawing schedules (opens the official source))