Plan reading for the California General Building exam
CSLB lists plans, specifications and project coordination in planning and estimating. These eight fictional project documents let you practice following a reference across schedules. Each one contains the information needed to solve its three questions.
Start 24 plan-reading questions
Trace the tag before pricing the work
Begin with the opening, space or work area named in the question. Find its tag in the schedule. Then check the revision register to see whether the change applies to that particular location. A price quotation alone does not release a change in the examples below.
Planning and estimating
1. Revision register and door hardware
Door schedule A6 issued May 2 lists lever set L1 for D12 and D14. Addendum 2, issued May 9, changes D12 only to L3. Bulletin 4, issued May 17, changes D14 to L2. A May 19 pricing note mentions L4 but is marked “budget option only; do not release.” Use the latest released change for each opening.
Framing and structural components
2. Wall framing detail index
Plan S2 tags interior walls W1 and W2. For W1 use detail 3/S5 at an uninterrupted run and 4/S5 at an opening. For W2 use 6/S5 at a return and 7/S5 at an opening. An index note sends wall-to-roof connections to S8. These callouts identify drawing references for this example.
Core trades
3. Equipment and control zones
Room schedule M1 assigns East Office and Copy Room to zone A; Meeting Room and West Office use zone B. Equipment schedule M3 assigns unit U1 and controller C1 to A, and U2 and C2 to B. An approved revision moves only Copy Room into B. All other room and equipment assignments stay as scheduled.
Finish trades
5. Surface finish and substitutions
Schedule A9 gives room 101 floor V1 and wall P1, room 102 floor T1 and wall P2, and room 103 floor V1 and wall P2. Bulletin F changes wall P2 to P3 in room 102 only. The owner requests T2 in room 103 by email, but the register lists that request as pending. Order only released finishes.
Planning and estimating
6. Roof work scope and exclusions
Bid scope R lists roof areas North and South. Base bid includes North tear-off and replacement, and South inspection only. Alternate A adds South replacement, excluding the skylight curb. Alternate B adds the curb only if A is accepted. The notice of award accepts the base and A, and expressly declines B.
Framing and structural components
7. Opening schedule and handoff
Opening list A7 calls for frame FR-A at doors 20 and 21 and FR-B at door 22. Frame FR-A uses detail J1 at a masonry wall and J2 at a stud wall. FR-B uses J3 at either wall. Door 20 is in masonry; doors 21 and 22 are in stud walls.
Safety
8. Site access phase plan
This project's site access sheet separates visitor and delivery gates. Phase 1 assigns visitors to Green and deliveries to Blue. Phase 2 sends visitors to West and deliveries to Blue. Phase 3 keeps visitors at West and moves deliveries to South. The signed phase log currently shows Phase 2. Gate changes require a new signed phase entry.