California private construction contract claims and retention

Follow a private construction payment from contract formation through retention, a documented claim, conference and mediation under the 2026 California rules.

Free preview: 4 questions. View study pass options for full access.

Included with the California Contractor study pass

The California Contractor Pass Kit: 5 printable study guides

Preview the printables below. Study pass holders can get the full PDFs from account downloads.

  • Blurred preview of Quick review sheet

    Quick review sheet

    Review eight worked examples from the published practice sets.

  • Blurred preview of Fold-and-review flashcards

    Fold-and-review flashcards

    Cut out the 24 rows and fold each down the center to hide the answer.

  • Blurred preview of 50-question practice workbook

    50-question practice workbook

    Answer each question on paper, then use the explained key to review missed topics.

  • Blurred preview of Study plan and score tracker

    Study plan and score tracker

    Choose a practice topic for each session and record your next step.

  • Blurred preview of Exam day checklist

    Exam day checklist

    Review the format and fill in your appointment details before you go.

Separate retention from a disputed change

A fictional payment file lists $80,000 in approved work, $4,000 held as retention and a separate $6,000 change request awaiting a decision. What amount can you reconcile from the approved work alone?

Check your reasoning

Subtract the recorded retention from the approved work to get $76,000 before other adjustments. Track the $6,000 request separately until its status is resolved. The amounts are assumptions for this file. To determine which legal rules govern a real project, first identify the contract date and project type.