Practice set
California private construction contract claims and retention
Free preview: 4 questions. View study pass options for full access.
Included with the California Contractor study pass
The California Contractor Pass Kit: 5 printable study guides
Preview the printables below. Study pass holders can get the full PDFs from account downloads.

Quick review sheet
Review eight worked examples from the published practice sets.

Fold-and-review flashcards
Cut out the 24 rows and fold each down the center to hide the answer.

50-question practice workbook
Answer each question on paper, then use the explained key to review missed topics.

Study plan and score tracker
Choose a practice topic for each session and record your next step.

Exam day checklist
Review the format and fill in your appointment details before you go.
Separate retention from a disputed change
A fictional payment file lists $80,000 in approved work, $4,000 held as retention and a separate $6,000 change request awaiting a decision. What amount can you reconcile from the approved work alone?
Check your reasoning
Subtract the recorded retention from the approved work to get $76,000 before other adjustments. Track the $6,000 request separately until its status is resolved. The amounts are assumptions for this file. To determine which legal rules govern a real project, first identify the contract date and project type.
Further reading: California Legislature · SB 61, private works retention
Choose a topic to practice
A warehouse payment file
A warehouse payment file.
3 questions in the bankComparing private projects
Comparing private projects.
3 questions in the bankA change to a packing plant
A change to a packing plant.
6 questions in the bankA disputed trade claim
A disputed trade claim.
5 questions in the bank