Finish schedules and trade handoffs

Use the drawing revisions, release log and installation notes to decide which work can proceed on each fictional project. Dimensions and approvals apply to the job shown.

Practice 16 finish coordination decisions

M2 · Museum welcome desk

  • Order of work: establish the desk centerline from grid G; install and level base cases; obtain signed field dimensions; release the stone top for cutting.
  • The west end has a scribe strip at the wall.
  • Fit the strip to the wall after leveling.
  • The east end has a finished panel facing the lobby.
  • At the return, keep the removable access panel clear of fixed shelving.
  • Revision 2 shifts the desk centerline 3 inches east of grid G.
  • All other notes stay in effect.

F6 · Clinic floor transitions

  • Room 21 receives sheet vinyl with an integral coved base.
  • Room 22 receives carpet tile and a separate wall base.
  • Detail T places the material break directly below the center of the closed door leaf.
  • The partition centerline lies 2 inches west of that location.
  • The release log requires a signed substrate test and approved adhesive sample before laying either finish.
  • Both samples are approved; only Room 22 has a signed substrate test.
  • Protect each finished floor with a loose cover before painters enter.
  • No adhesive tape may touch the finish.

R4 · Gallery ceiling and access

  • Use the reflected ceiling plan for grid layout.
  • Center the grid on axis C; equal cuts at the north and south walls take precedence over the preliminary tile count.
  • Panel AP3 must remain removable below valve V3.
  • If a light conflicts with AP3, shift the light to the adjacent east bay and retain the access location.
  • Close the gypsum border only after the above-ceiling walk is signed.
  • The walk log marks the west border released and the east border pending.
  • Trim rings go on after the border receives its final coat.

T3 · Market hall tile and coatings

  • Set the tile pattern from the center of the service opening, not the midpoint of the long wall.
  • Tile stops at the underside of shelf S; above S use the washable wall coating.
  • At joint J carry the substrate movement joint through the tile finish using the specified flexible joint detail.
  • The grout sample under the final lamps must be signed before production grouting.
  • The site has a signed sample under temporary lamps only.
  • Install the painted trim cap after both tile grouting and the final wall coat are complete.

The state outline assigns approximately 20% of the General Building exam to finish trades, including floor covering, tile, millwork and ceilings. Read the CSLB examination guide.